- Dead load signifies self weight of structure.
- DPC stands for Damp Proof Course. The density of DPC should not remain below 2.5 cm.
- If the sand contains in excess of 5% moisture content, that should not be applicable for concrete mix.
- The curing period of RCC is 28 days.
- Ties belong to the transverse reinforcement that is arranged in columns.
- The stirrups belong to the transverse reinforcement in beams.
- The purpose of stirrups in beams and ties in columns is to manage the shear force as well as retain the longitudinal bars in exact location.
- M20 grade of concrete should be applied in slab construction. The ratio of mix should be 1:1.5:3
Also read : CIVIL ENGINEERING SOLVED PROBLEMS, 8TH ED – AN EXCLUSIVE E-BOOK FOR NCEES CIVIL PE EXAM PREPARATION
- The length of the hook should not remain below 9D where D stands for dia of bars.
- The rise in stairs should be among 150 mm to 200 mm.
- Tread in staircase should be among 250 mm to 300 mm.
- The slope or pitch of the stair should remain among 25 degrees to 40 degrees.
- Unit weight of PCC is 24 KN/m2, RCC is 25 KN/m2 and steel is 7850 kg/m2.
- If the cement is over 3 months old, then it should be utilized for construction.